Construction on the University of Minnesota, Morris’ Green Prairie Living and Learning Center is moving forward on schedule, but casual observers may not see much progress until the weather improves. Adding the brick and stucco work on the outside of the building is on hold until overnight temperatures stay above 40 degrees. (Kim Ukura/Sun Tribune)

Cold overnight temperatures delay exterior progress on UMM’s Green Dorm

Email

MORRIS – The late arrival of spring temperatures has delayed work finishing the exterior of the Green Prairie Living and Learning Center at the University of Minnesota, Morris, but work on the interior has moved quickly since the building was fully enclosed.

“There's always something that can come up, but I feel pretty confident that this building will be occupied before the school year starts,” said Rick Lock, site supervisor with McGough Construction.

Are you a newspaper subscriber but you don't have a Digital Access account yet? You can activate your account here: Activate All Access.

You will need your subscription account number and phone number. Not sure if you have an account? Email us at subscriberservices@forumcomm.com and we can help you.

Advertisement
kukur

Kim Ukura is the editor of the Morris Sun Tribune. 

Advertisement
Advertisement
randomness