EPA puts hold on Big Stone II

The Environmental Protection Agency on Friday issued objections to an air quality permit for the Big Stone II coal-fired power plant in Milbank, S.D., a move that doesn't kill the project but does mean South Dakota officials will have to change the permit request to meet federal requirements within 90 days.

Advertisement

The EPA announced its decision just days after the Minnesota Public Utilities Commission approved with conditions a proposal from utilities to build powerlines to carry energy from the planned addition to the exisiting Big Stone plant.

If the plant is required to make significant changes to the permit request to comply with EPA standards, the powerline decision could be affected.

The EPA stated that Big Stone II officials have 90 days to change their permit to satisfy regulations for air quality.

According to various news reports, groups objecting to the plant declared the EPA's decision a major victory while others are less optimistic that the EPA's move spells an end to the facility.

Big Stone Power II is estimated to cost more than $1.5 billion to build.


Similar Articles

An existing 230-kilovolt power line is shown Wednesday near Granite Falls. The now-defunct Big Stone II project included plans to upgrade transmission capacity on two corridors.

By Al Edenloff and Don Davis Forum Communications The remaining partners in a South Dakota coal-fired power plant that was to provide electricity to Upper Midwestern states announced Monday they ...

WILLMAR -- The decision by the lead utility to withdraw from the proposed Big Stone II power plant project does not necessarily mean the plant is dead because another utility ...

Otter Tail Power Company announced Friday afternoon that it will withdraw from the Big Stone II power plant near Milbank, S.D., that was to be operating by 2011, the company ...